Cima P1 Exam Question No 29

Question No 29:

The company has now established that there is a stepped increase in fixed costs of $30,000 when output reaches 180,000 units.
The estimate of total costs for an output of 175,000 units using the additional information is:

A.
$2,645,000
B.
$2,275,000
C.
$2,615,000
D.
$2,630,000

Answer: C