Cima P1 Exam Question No 32

Question No 32:

FP has decided not to use the EOQ and has decided to order 2,600 calculators each time an order is placed. The total ordering and holding costs per annum will be?

A.
$5,240
B.
$19,800
C.
$208,014
D.
$3,420

Answer: C